Scope : Conceptual, Detailed Design and Technical asistance during Construction
Coordinator : Javier Manterola Armisen
Project Manager : Miguel Angel Astiz
End Year Construction : 2003
Typology : Moveable Bridges
Team : Javier Manterola Armisén, Miguel Ángel Astiz Suárez
GeopositionView Project

This bascule bridge is situated on the land strip of La Manga del Mar Menor, Murcia. It replaces an old metal, swing bridge that hardly solved the increasing vehicle and vessel traffic on their way from the marina in the Mar Menor to the sea Mayor side. The bridge was given a height large enough to allow for an uninterrupted crossing, with the exception of very tall-masted vessels.