The construction of the River Barrow Bridge is advancing quickly.

insta_mavic production

The construction of the River Barrow Bridge is advancing quickly.

Presently 7 out 19 cables have been stressed at the central pylon and 3 out of 9 cables have been stressed at the lateral pylons.

The cantilevers are about 64 m long from the central pylon and 41 m long from the lateral pylons.

The West approach spans are finalized and in the East approach spans the traveller is placing the overhangs in the last two spans.