Cadiz Bay Bridge. Reaching the compensation span piers with a 218.5 m cantilever with no back stays.

Juan Antonio Navarro,  a senior engineer with CFC, explains how the cantilever deck, without any kind of  back stays (218.5 m long on the midspan side and 198.5 m long on the compensation span side), is about to reach the first pier of the compensation span, as we can see in the...
By :
Comments : Off

The Alcántara Bridge: the arch execution begins.

Borja Martín Martínez, a CFCSL civil engineer, updates us on the current progress on this bridge. The execution of the central arch is just beginning. It has a 324 m long span and its height is 90 m above the average reservoir water level (point 3 of the figure below):  ...